Now 97% leased with the building complete, Centre 10 has welcomed our first occupants, Mawer Investment Management, on Monday November 18th. Other tenant improvements are also underway throughout the building and by Spring 2014 the building will be fully built out.
With curtain wall framing complete and the cranes starting to come down, we quickly near the final phases of our building shell construction - a strong signal to market that we are nearly ready!!
Roofing and patio details, including our second floor patio are underway ~ just in time for Calgary's summer months.
Just like a cherry is to an ice cream sundae, Centre 10’s concrete structure was “topped off” early March with wall installations & curtain wall glazing nearly finished.
Tenant improvements for our first of many tenants ~ National Energy Board, are just getting started in conjunction with elevator and rooftop mechanical equipment installations underway.